You need a QBCC Owner-builder permit before starting building work valued at more than A$11,000 (including GST) on your own land if you intend to run the job yourself and not hire a licensed builder. One applicant must have done an owner-builder course in the past five years, and in most cases you can hold only one permit every six years.

How the value is worked out

The A$11,000 test uses what a QBCC-licensed contractor would charge: materials and labour at trade price with GST, even if your brother-in-law is working for free and the timber is salvaged. If costs rise during the job you are expected to tell the QBCC with an amendment form. Farm buildings have their own figure of A$27,500. Both numbers are on the QBCC About Owner-building page.

Who can apply

You must be on the property title, a director of the company that owns the land, or a lessee with the owner's written permission. You are ruled out if you have a Tier 1 defective work notice, unpaid QBCC infringement fines, a permit cancelled in the last three years, or a permit issued in the last six (exemptions to the six year rule are sometimes granted).

What to have ready

The QBCC says applications are usually processed within 30 working days. Nothing can start on site before the permit is issued, excavation included, and your certifier cannot sign off plans until they have seen it. See the QBCC application page; current charges are on its fees page.

What a permit does not let you do

An owner-builder acts as head contractor: you engage the trades and schedule the work. You still cannot do plumbing, drainage, gas fitting or pest control without the occupational licence, fire protection work, or mechanical services work over A$1,100. You cannot remove more than 10 square metres of asbestos. The permit does not stretch to commercial or industrial buildings, or to multiple dwellings such as a duplex or an attached granny flat.

The trade-offs people miss

No home warranty insurance. Owner-builders cannot access the Queensland Home Warranty Scheme. If a trade walks off or the slab subsides, there is no scheme to claim on.

A notice on your title. The permit creates an "Owner-builder administrative advice" on the title that stays for seven years. Sell within six years of the completion date and you must tell the buyer in writing.

For a simple shed or deck that pushes past A$11,000 the permit can make sense. For a whole house, compare the saving with the loss of insurance and the hours of supervision before deciding. If you would sooner hire, start with which builder class fits the job.

Quick answers

Can an owner-builder build a duplex?

No. The QBCC lists multiple dwellings, such as duplexes, attached granny flats and units, among the work an owner-builder cannot do.

Does owner-builder work have home warranty insurance?

No. The QBCC states that owner-builders cannot access the Queensland Home Warranty Scheme.