Payments
How should progress payments work on a Queensland build?
Once a domestic building contract is over A$3,300, you and the contractor agree how many progress payments there will be and when they fall due, but every claim has to be in proportion to the work actually completed. A builder cannot claim half the price until at least half the on-site work is done.
The rule in one line
The QBCC deposits and progress payments page puts it this way: all payments must be relative to the work completed. Its example is that the contractor cannot claim more than 50% of the contract price, counting the deposit, until at least 50% of the work on site has been finished.
A worked example
Take a A$240,000 extension on a level 2 contract. The deposit cap is 5%, or A$12,000. Suppose the schedule then lists slab, frame, enclosed, fixing and practical completion stages. When the frame claim arrives, add up everything claimed so far including the deposit. If that total is A$130,000, the builder is saying that more than 54% of the job is physically complete. Walk the site. If the frame is up but the roof is not on, the claim is ahead of the work and you are entitled to question it before paying.
Stage claims and time-based claims
Most house contracts tie payments to stages. Some renovation contracts bill at regular intervals instead, fortnightly or monthly. The QBCC says a contractor claiming at intervals should back each claim with detailed evidence of the work performed in that period. Ask for it in writing: a short list of what was done, with photos, is normal practice for a well run job.
Habits that protect you
- Pay on the due date in the contract, not before it. Paying early reduces what the Home Warranty Scheme will cover.
- Never pay more than the amount the contract says is due for that stage.
- Check a stage is complete before paying for it. If a certifier inspection belongs to that stage, ask for the result.
- Keep every invoice, receipt and variation. You will need them if a claim is ever made.
- Hold the final payment until you have checked that all agreed work is finished.
The QBCC also recommends getting realistic quotes and choosing a fixed-price contract over a cost-plus or construction management arrangement. The reasons are in cost-plus contracts and preliminary agreements.
When the price changes mid-job
Extra work has to go through a written variation that states the price change and the date it is payable. A verbal "we will sort it out at the end" is how final invoices blow out. See contract variations.
Quick answers
Can my builder ask for 50% before the job is half done?
No. The QBCC example is that no more than 50% of the contract price, including the deposit, can be claimed until at least 50% of the on-site work is complete.