How do variations to a building contract work in Queensland?
A variation is any change to the contract after it is signed, such as different materials or extra work. In Queensland the contractor must give it to you in writing before the varied work starts or within five business days of you both agreeing to it, whichever is earlier, and you must reply in writing to say whether you agree.
What the document has to say
- a description of the change
- the date it was requested
- the contractor's reasonable estimate of any delay it will cause
- the change to the contract price, or how it will be calculated, and the date an increase is payable or a decrease credited
The QBCC says the paperwork is usually its Form 4 or Form 5, depending on the contract type. The requirements are listed on the QBCC contract variations page.
The one exception
Urgent work, for example something needed for safety, can go ahead without the written copy first where producing it is not reasonably practicable. A burst pipe behind a wall that has just been opened is the kind of thing meant. A change of benchtop is not.
An example
Midway through a renovation you decide to swap laminate benchtops for stone and move a doorway. The builder should hand you a variation that prices both, says the doorway will add four working days, and states that the extra is payable with the fixing stage claim. You sign or reply by email to accept. Only then does the joiner get the new order. If instead the changes are agreed across the kitchen bench and first appear on the final invoice, you have a dispute about price and time with nothing in writing on either side.
Effect on home warranty insurance
If a variation changes the value of the project, the contractor must amend the home warranty cover. Where the price drops, the QBCC pays any premium refund to you or the contractor depending on the contract arrangements, and you may need to show what premium you paid. Keep variations with your contract papers: they are evidence if you ever make a claim.
Our view on volume
A handful of variations on a renovation is normal, because old houses hide things. A long run of them on a new build from finished drawings usually points to a thin specification at contract stage. Fixing selections before signing is cheaper than varying them later, and each variation is another payment to track against the progress payment schedule.
Quick answers
Can a builder charge for a variation I did not agree to in writing?
The QBCC says the contractor must give you the variation in writing before the work starts or within five business days of agreement, and you must respond in writing. The exception is urgent work where a written copy first is not reasonably practicable.
Sources
All sources were opened in November 2026.
General information for Queensland home owners, written by the Bluegum Builders editorial desk in November 2026. It is not legal advice. Figures and rules change, so confirm them on the linked QBCC pages before acting.