Should I sign a cost-plus building contract in Queensland?

Be careful. The QBCC does not recommend cost-plus contracts for residential work, says final costs often land 50% to 100% above expectations, and confirms that non-completion protection under the Home Warranty Scheme is not available for cost-plus or construction management contracts. A fixed-price contract keeps both the price and the insurance intact.

What makes a contract "cost-plus"

On the QBCC's definition, it is a contract where the final price cannot be accurately calculated when it is signed, even leaving aside prime cost items and provisional sums. You pay the actual cost of labour and materials plus a margin. The builder carries little price risk; you carry nearly all of it.

Construction management is a different animal again

Under a construction management contract you may have to engage the trades directly and take responsibility for how they perform. It can look like a cheaper way to use a builder's contacts. In practice you become the party every subcontractor has a contract with, and the QBCC recommends formal legal advice before using either form. Both warnings are on its contracts and agreement types page.

The insurance gap

This is the part we think matters most. Under a fixed-price contract, the Queensland Home Warranty Scheme can respond if the builder fails to finish. Under cost-plus it cannot, because there is no fixed price to measure the unfinished work against; cover is limited to defective work. The QBCC home warranty page says the same thing from the insurance side. On a house build, non-completion is the expensive risk.

When owners still choose it

Heritage restorations and repairs after fire or flood are sometimes genuinely unpriceable up front. If you go this way, some owners negotiate a budget estimate in writing, open-book invoices with every claim, an agreed margin percentage, and a right to stop at defined points. None of those are QBCC requirements; they are ordinary commercial protections, and a solicitor can draft them.

Preliminary agreements

A preliminary agreement lets a builder charge up front for early work such as designs, plans, soil tests or surveys before the main contract exists. The QBCC warns that some include fees or penalties if you do not go on to build, that such terms "may be illegal", and that legal advice is wise. Before paying, ask two things: who owns the drawings and reports if you walk away, and whether the fee is credited against the contract price if you proceed.

Once you do sign a fixed-price contract, the deposit caps and cooling-off period apply as usual.

Quick answers

Does home warranty insurance cover a cost-plus contract?

Only for defective work. The QBCC says cost-plus contracts are not covered for non-completion because the final price is uncertain.