How long do I have to make a home warranty claim in Queensland?
Cover runs for six years and six months, but each kind of claim has a far shorter window. A non-completion claim must be lodged within three months of the contract ending. A structural defect must be claimed within three months of you noticing it. A non-structural defect must be claimed within seven months of the work being substantially complete.
The deadlines
| Claim | Condition | Lodge within |
|---|---|---|
| Non-completion | The contract must end within 2 years of work starting, or within 2 years of the contract date if work never started | 3 months after the contract ends |
| Structural defect | You first become aware of it within 6 years 6 months of cover starting | 3 months of becoming aware |
| Non-structural defect | You first become aware of it within 6 months of substantial completion | 7 months of substantial completion |
All from the QBCC time limits page.
When cover starts
On the earliest of three events: the premium being paid, the contract being entered into, or work starting. The six years and six months run from that day, not from handover. On a build that takes fourteen months, more than a year of the cover period has gone before you move in. The QBCC notes cover may be extended where the work takes longer than six months to complete.
Non-completion needs a properly ended contract
A non-completion claim generally requires the contract to have been lawfully terminated, with exceptions such as the contractor's death or deregistration. Terminating wrongly can put you in breach, so the QBCC strongly recommends legal advice before you do it. The three month lodgement period starts when the contract ends, which makes the order of events important: advice first, then termination, then the claim.
The seven month trap
Non-structural covers the things owners most often find: sticking doors, poor paint, a leaking shower screen. You have six months from substantial completion to notice them and seven to claim. Walk through the house at month five with a notepad. Send the builder a written list, because the QBCC complaint process needs written notice in any case, and lodge before month seven if the list is not dealt with.
Subsidence
The QBCC handles subsidence by way of a defective work complaint. It may engage an engineer and monitor movement over time, so these matters can run for a long while. The time limits page does not give a separate subsidence deadline; treat the structural limits as your guide and confirm with the QBCC on 139 333.
For what the policy pays, see how home warranty insurance works.
Quick answers
When does the 6 years 6 months of cover start?
On the earliest of the premium being paid, the contract being entered into, or work starting, according to the QBCC.
How long do I have to claim for a non-structural defect?
Seven months from the day the work is substantially complete, and you must have first noticed the defect within six months of that day.
Sources
- QBCC: Time limits for cover and claims
- QBCC: Help with building issues and disputes
- QBCC: Who pays the premium
All sources were opened in November 2026.
General information for Queensland home owners, written by the Bluegum Builders editorial desk in November 2026. It is not legal advice. Figures and rules change, so confirm them on the linked QBCC pages before acting.